Projects update meeting 2022-04-06

From GO Wiki
Revision as of 02:41, 1 April 2022 by Pascale (talk | contribs)
Jump to navigation Jump to search

Attendees

  • Members: David, Huaiyu, Kimberly, Pascale, Seth, Suzi, Paul, Chris, Cynthia
  • Present: David, Pascale, Seth, Suzi, Huaiyu,
  • Regrets: Chris, Cynthia, Kimberly

Announcements

Google drive move

Project updates

Task Matrix

Main tasks - Jan-July 2022

Completed projects?

Project status

Ongoing data QC and pipeline maintenance

Anything to report? what resources are needed until the next release?

Alliance software support

Need to define PI, deliverables, resource

Ontology single BP jamboree this week

Monday - Thursday


Currently active projects

Project name Link to GH project Resources: PI, PO, TL, Other resources Next review Follow up review Aligned with Matrix? Notes
Software improvement
Finalize AmiGO default relation change (Aim 3) AmiGO default relation GH project PI: Chris, PO:Chris, TL: Seth, Others: Seth 2022-03-30 Yes To review and close after the next release. Webpage on relations need improvement (Chris, Pascale)
Software improvements : GO API GO API PI: Chris, PO:??, TL: Seth, Others: Sierra Review status 2022-04-20 Yes Will review at the end of April to see the status of the project
Software improvements : pipeline cleanup PLANNING Pipeline cleanup PI: Chris, PO:??, TL: Seth, Others: Seth, Dustin, Sujay? Review specs & scope 2022-04-20 Yes Planned for April
Alliance software support Alliance software support PI: , PO:??, TL: Seth, Others: 2022-03-23 No
Noctua improvement and maintenance Noctua 2021 & Noctua 2020 PI: Paul , PO: Kimberly, TL: Seth, Others: Tremayne, Jim 2022-03-23 2022-04-05 No
GO_REFs GO_REFs PI: Chris, PO: Chris, TL: Seth, Others: Sujay, some of Sierra 2022-04-20 Yes
Ongoing data QC and pipeline maintenance Ongoing data QC and pipeline maintenance PI: Chris, PO:Pascale, TL: Seth, Others: Seth, Dustin, Sujay, Jim? Ad hoc if there is a big bug Yes
Essential software maintenance Essential software maintenance PI: Chris, PO:Pascale, TL: Seth, Others: Seth, Dustin, Sujay, Jim? Ad hoc if there is a big bug Yes
Remove some main roadblocks for GO-CAM models curation (Aim 2)
NEO load of new sequences NEO load GH project PI: Chris, PO: Pascale , TL:, Seth Others: Sujay 2022-03-30 Yes Seth will look into a strategy - week of March 16th
New visual editor (Tremayne) -> ready to push to Noctua dev? Visual Pathway editor GH project PI: Paul, PO: Paul, TL:, Others: Tremayne 2022-03-23 Yes Ready for release to prod? Present at a future annotation call - or GOC meeting
Model copy PLANNED Old Shallow Model Copy GH project PI: Paul, PO: Kimberly, TL: Jim, Others: Tremayne 2022-03-30 - Review status Yes Aim to present at GOC meeting (or announce work is ongoing)
Noctua output GPAD output PI: Chris, PO: Kimberly, TL:?, Others: Jim 2022-03-30 - Review specs +/- : Planned for March, but project not yet defined or resourced David will split into 3 projects: (1) GPAD for MOD imports (done); (2) remove redundancy in exports (high priority); (3) problems with complicated models
Simple version of automation of Noctua updates Noctua updates PI: Chris, PO: TBD, TL: Seth, Others: 2022-03-30 - Review status Yes
Complete MOD imports (Aim 2)
MOD imports MGI - WB - SGD PI: Chris, PO: Kimberly, TL: Seth, Others: David, Suzi, Dustin 2022-03-23 2022-04-05 MGI done? No
Annotation Extension Relation Review Annotation Extension Relation Review PI: , PO: Kimberly, TL: , Others: David, Dustin, Pascale TBD - after some projects are closed
Integrate YeastPathways in GO Cam Yeast Pathways PI: Paul, PO: , TL: Dustin, Others: 2022-03-30 No
Ontology (Aim 1)
Phylogenetic taxon constraints TC GH project - ontology repo PI: Paul, PO: Pascale, TL: Jim, Others: 2022-04-20 Yes
Outreach/usability (Aim 3)
Switch to “species” for download outputs PLANNED Improved Downloads ???? PI: , PO:, TL:, Others: 2022-03-23 - Review specs No
Manage users more actively (+ all contributing groups, in particular those not attending GOC and annotation calls) PI: Mike , PO: Suzi, TL:, Others: 2022-04-xx before the GOC meeting No
Noctua training material Noctua training Project PI: Mike , PO: Suzi, TL: NA, Others: David 2022-04-20 Yes After/around the ZFIN training session
Other projects