Projects update meeting 2022-10-26
Attendees
- Members: David, Huaiyu, Kimberly, Pascale, Seth, Suzi, Paul, Chris, Cynthia
- Present:
- Regrets:
Resources
Berkeley
- Seth 80%
- Sierra 20%
Jim
- 30%
MGI
- Harold 75%
- David 67%
SGD
- Suzi:100 %
- Edith 10%?
USC
- Pascale 100%
- Tremayne: 40%
- Dustin: 40%
- Anushya: 50%
- Marc 50%
WormBase
- Raymond: 100% ?
- Kimberly: 30-40%
Documents
Proposed priorities for the next 6 months
Projects
Update on ongoing work
Active projects - Week of Oct 24
Staff | Project 1 | Project 2 | Project 3 | Project 4 | Aligned with Matrix? | Notes |
---|---|---|---|---|---|---|
David | Relations to link MF - documentation | Annotation Extension Relations in Noctua | All Reactome projects | |||
Dustin | Essential software maintenance & QC and pipeline | Panther 17? | Yes | |||
Kimberly | Relations to link MF | WormBase - Noctua migration | Annotation Extension Relations in Noctua | Ongoing Noctua maintenance and Annotation Calls | Yes | |
Jim | Annotation Extension Relations in Noctua | Ongoing - QC and pipeline (ontology support) | ||||
Sierra | Annotation Extension Relations in Noctua | API | Yes | |||
Seth | Essential software maintenance & QC and pipeline & Noctua routine maintenance | JSON for GO-CAM API (essentials) | ||||
Suzi | ||||||
Pascale | Relations to link MF | BP refactoring | Ongoing - Management (~20-25%) | |||
Tremayne | Annotation Extension Relations in Noctua | VPE ? | Pathways widget ? | |||
Anushya | ||||||
Harold | Ontology | |||||
Raymond | Ontology | |||||
Marc | PAINT (40%), GO-CAM models (10%) |
Update on ongoing projects
Project | PI | PO | TL | Other resources | Delivery or next review date | Any blocking issues? | |
---|---|---|---|---|---|---|---|
Relations to link MF | Paul T | Kimberly | - | David, Pascale | https://github.com/oborel/obo-relations/pull/635; also, what is the RO release cycle? | ||
API | Chris | Chris | Seth | Sierra, Dustin, Tremayne | |||
Maintenance:
|
NA | ||||||
WB and SGD load | Started week of October 17th | TBD | Kimberly (WB), Suzi (SGD)? | TBD | TBD | ||
Annotation Extension Relations in Noctua | Paul | Kimberly | Seth | David, Dustin, Tremayne, Jim | Is this ongoing ? Draft requirements doc (still WIP): https://docs.google.com/document/d/10lw_6OQF0XOVhInkZoJiRnBlR_m-mGqByb9DtRn_LYQ | ||
GO-CAM enrichment | Chris (Paul S) | Kimberly (I'm not spending much time on this, but Nick needs some more feedback/input.) | Dustin | Kimberly, Jim, Dustin | |||
Reactome projects: |
|
|
|
|
|||
VPE | Paul | Paul | ? | Tremayne | |||
Google drive move | Chris | Suzi | Seth | All managers | Any remaining tasks?
| ||
Yeast pathways | Paul T | Suzi | Dustin | ||||
Pathways widget | Paul T TBC | TBD | TBD | Tremayne ? | Project is closed; do we have specs and deliverables for this? | ||
Next projects
Project | Scheduled for (time frame) | PI | PO | TL | Other resources | Project specs document | Is project sufficiently defined? Any blocking issues? |
---|---|---|---|---|---|---|---|
GORULES (low-hanging fruit) | TBD | Pascale | Dustin | Tremayne? Anushya? Seth? | Specs: Can draw from (and CLOSE): https://github.com/orgs/geneontology/projects/47 https://github.com/orgs/geneontology/projects/40 | ||
Update Noctua documentation | TBD | TBD | NA | Pascale, Patrick Masson To be reviewed by Kimberly, David, Suzi | |||
PLANNING GO-CAM API (merge public APIs) | Chris TBC | Chris TBC | Seth TBC | Sierra | Specs & deliverables to be defined | ||
# | |||||||
# | |||||||
# | |||||||
# |